A complete project, in the order of the four tabs: Well → Test → Results → Report. Every field saves itself to the session as you type and the calculation updates at every change: there is no "Calculate" button. You can go back to an earlier tab at any time; the results follow the data.

0. Start a project

From the File menu:

  • New project empties the session;
  • Open… reopens a GeoTheis NX .geotheisnx file or a .wtax file from the desktop program. With a .wtax you get Desktop program project opened: check the data before calculating., with the import notes;
  • Examples with tests and Single wells (known critical discharge) open the examples of the desktop program.

If the project on screen has changes that are not in a file, the program first asks whether to save them. Type the Project name at the top of the page (for example Well P1 — Rossi farm): it names the file and the report.

1. Well tab

There are four panels on the left; on the right the Well section is redrawn at every save. All the fields are described in Well.

  1. Site and coordinates — Search for the town or the street, then click the exact spot of the well, or use GPS position or type the coordinates in one of the systems offered (WGS84, UTM, Gauss-Boaga, ED50). The program suggests the municipality and the ground elevation from the digital terrain model (DTM): the project's ground level changes only if you press Use the DTM elevation. Check the Registered wells nearby (ISPRA archive). If you have the well coordinates from another source, compare them in Check against a second source.
  2. Stratigraphy — One layer per row, from ground level downwards: soil, description, thickness. It is used for the drawing and the report, not for the calculation.
  3. Well and aquifer — Four tabs:
    • Aquifer and levels: Aquifer type, Well penetration, Construction and the elevations in m a.s.l. The aquifer type decides which methods apply: always choose it.
    • Calculation scheme: well radius, depth, blank between head and screen, screen length and, for partially penetrating wells, the data towards the base. This is what the formulas use.
    • Completion: borehole, casing (blank, screens, sump), annulus, conductor casing, pump, measured levels. To get going quickly, press Propose completion from scheme in the Calculation scheme tab.
    • Job: client, project, test date, contractor, engineer, description and notes for the report.
  4. Piezometers — Name and Distance r from the well axis for each piezometer: the distance is the only piezometer input used by the calculation. Elevations and screen are for the drawing. Without piezometers the test is analysed on the pumped well only, and S cannot be derived reliably.

If something does not add up (static level above ground level, aquifer top below the base, a radius of 5 m…) the Data to check strip appears. It does not block anything: it asks you to check.

2. Test tab

Two panels, described in Tests:

  1. Step-drawdown test — One row per step, with the end-of-step reading: time from the start of the test, discharge and cumulative drawdowns in the well and in the piezometers. Choose the units in Times in and Discharges in. With Paste from Excel or CSV you copy the columns from a spreadsheet or from the datalogger.
  2. Constant rate and recovery — Test discharge, Steady-state drawdowns (at steady state, for Dupuit-Thiem), Pumping readings (t from the start of pumping) and Recovery readings (t′ since the pump stopped), in the well and in the piezometers.

If you do not have a step-drawdown test but you know the critical discharge of the well, fill in the Known critical discharge (no step-drawdown test) panel: together with the well geometry it feeds the single-well methods, which give indicative T and K.

3. Results tab

  1. Read Methods calculated and Not applicable to the data: a missing method has its reason written next to it.
  2. Check the Comparison of methods and the Deviations to check.
  3. Open the method tabs. On the charts, exclude anomalous readings with a click, narrow the Cooper-Jacob interval, adjust the Theis or Hantush type curve if needed.
  4. With a step-drawdown test, choose the critical discharge on the characteristic curve.
  5. Confirm the Design value (T, K, S, R) and the Allowable discharge, or choose another method or type the operating discharge.

Everything is free. Details are in Results; the methods and their assumptions in Methods.

4. Report tab

  1. Read What goes into the report: each item says whether the data are there (position, stratigraphy, steps, constant rate, piezometers).
  2. Check the Preview, which is free: it is the same text as the Word file.
  3. Generate Word to download the report, Well DXF for the section as DXF: both use credits.
  4. In Continue with the other NX apps send the well to GeoDropbox, open the section in CAD Tools or the site dossier in Atlante.

See Report.

5. Save

The project lives in the session and expires after 30 minutes of inactivity. Save it with File → Save (Ctrl+S) or Save as… (Ctrl+Shift+S) to a .geotheisnx file, or to GeoDropbox. See Files and GeoDropbox.

Tip

The Assistant at the top reads the project and the results and can enter data for you: pasted readings, stratigraphy, piezometers, well coordinates. Each message uses credits. See Assistant.